Analisis Optimasi Durasi dan Alokasi Tenaga Kerja Menggunakan Metode Crashing dan Resource Leveling (Studi Kasus Pembangunan Gedung Inspektorat Provinsi Kalimantan Selatan)
DOI:
https://doi.org/10.31004/riggs.v5i2.7762Keywords:
Crashing, Resource Leveling, Tenaga Kerja, Penjadwalan Proyek, Microsoft ProjectAbstract
Construction projects in the building sector frequently encounter scheduling deviations caused by supply chain disruptions or unforeseen technical constraints. In the case of the Inspectorate Building Construction Project of South Kalimantan Province—executed by PT. Megatama Karya with a contract value of Rp 19,000,000,000—a critical delay occurred during the pile driving phase, necessitating schedule acceleration. This study aims to analyze and optimize project duration and labor allocation by integrating schedule crashing and resource leveling methods, modeled using Microsoft Project 2016. The research employs a quantitative approach, utilizing secondary data comprising the Bill of Quantities (BOQ), work volume, and SNI-based labor coefficients. Three scheduling scenarios were simulated: (1) Normal (baseline), with project completion on March 9, 2026; (2) Crashing, with completion advanced to December 23, 2025, but resulting in extreme overallocation peaking at 110 unskilled laborers per day; and (3) Integrated Crashing + Leveling, which produced an optimal completion date of February 4, 2026—33 days earlier than the baseline—while maintaining labor demand within the contractor's maximum capacity of 55 unskilled laborers, 60 carpenters, 40 steel workers, and 15 masons. The integration of both methods proved effective in achieving time
Downloads
References
[1] Badan Pusat Statistik, Statistik Konstruksi Indonesia 2021–2023. Jakarta, Indonesia: BPS, 2023.
[2] A. I. Alfarisi, E. Handayani, and K. R. Amalia, “Analisa koefisien harga satuan tenaga kerja di lapangan dengan analisa SNI struktur bangunan gedung,” Jurnal Talenta Sipil, vol. 5, no. 2, pp. 222–228, 2022, doi: 10.33087/talentasipil.v5i2.116.
[3] R. Wintan and O. Gondokusumo, “Resource leveling using two-stage scheduling model for a highway construction project at Jakarta,” International Journal of Application on Sciences, Technology and Engineering, vol. 1, no. 2, pp. 778–797, 2023, doi: 10.24912/ijaste.v1.i2.778-797.
[4] I. G. N. Sunatha, N. L. M. A. M. Pradnyadari, and N. M. D. Wintari, “Analisis resource leveling pada proyek pembangunan Rusun Aspol Sanglah T.36 bertingkat 4 lantai,” Jurnal Ilmiah Kurva Teknik, vol. 11, no. 2, pp. 45–53, 2022, doi: 10.36733/jikt.v11i2.5429.
[5] A. Purwantoro, A. W. L. To’unni, and S. A. K. A. Uda, “Optimalisasi alokasi tenaga kerja menggunakan resource leveling,” Jurnal Saintis, vol. 23, no. 2, pp. 19–26, 2023, doi: 10.25299/saintis.2023.vol23(02).14478.
[6] M. Adil, L. Lusiana, and S. Syahrudin, “Optimalisasi biaya dan waktu proyek menggunakan metode crashing dengan penambahan waktu kerja lembur dan sistem kerja shift,” JeLAST: Jurnal Teknik Kelautan, PWK, Sipil, dan Tambang, vol. 10, no. 1, 2023, doi: 10.26418/jelast.v10i1.62949.
[7] G. D. J. Retor and F. J. Oei, “Analisis pengendalian proyek dengan metode crashing pada proyek PT X di Jakarta,” JMTS: Jurnal Mitra Teknik Sipil, vol. 6, no. 4, 2023, doi: 10.24912/jmts.v6i4.24974.
[8] M. Rivaldy, I. Oppier, F. A. Sangadji, and S. I. Latuconsina, “Optimalisasi pelaksanaan pekerjaan dengan menggunakan metode crashing pada pembangunan Rumah Susun Pemerintah Kota Tual,” Jurnal MESIL, vol. 4, no. 1, pp. 11–16, 2023, doi: 10.53695/jm.v4i1.834.
[9] Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK Guide), 7th ed. Newtown Square, PA, USA: PMI, 2021.
[10] D. P. Retno, A. Astuti, and Z. Tamimi, “Analisa penggunaan sumber daya manusia dengan metode resource leveling pada pelaksanaan proyek konstruksi,” Jurnal Saintis, vol. 18, no. 1, 2018, doi: 10.25299/saintis.2018.vol18(1).3194.
[11] H. Ding, C. Zhuang, and J. Liu, “Extensions of the resource-constrained project scheduling problem,” Automation in Construction, vol. 153, art. no. 104958, 2023, doi: 10.1016/j.autcon.2023.104958.
[12] W. Peng, X. Lin, and H. Li, “Critical chain based proactive-reactive scheduling for resource-constrained project scheduling under uncertainty,” Expert Systems with Applications, vol. 214, art. no. 119188, 2023, doi: 10.1016/j.eswa.2022.119188.
[13] P. R. Maulidah, “Analisis kebutuhan sumber daya tenaga kerja pada pelaksanaan Proyek Rumah Sakit UNIMUS menggunakan metode resource levelling,” Skripsi, Universitas Negeri Semarang, Semarang, Indonesia, 2023.
[14] D. Fardila and N. R. Adawyah, “Optimasi biaya dan waktu proyek konstruksi dengan lembur dan penambahan tenaga kerja,” INERSIA, vol. 17, no. 1, pp. 35–46, 2021, doi: 10.21831/inersia.v17i1.39499.
[15] W. Liu, L. Ge, C. Qu, and S. Yang, “Bi-objective optimization for resource-constrained robust construction project scheduling,” KSCE Journal of Civil Engineering, vol. 28, no. 1, pp. 15–28, 2024, doi: 10.1007/s12205-023-0633-8.
[16] I. S. I. Salu, A. S. Raintung, and S. S. Peginusa, “Peningkatan efisiensi pemanfaatan tenaga kerja melalui metode resource leveling: Studi kasus Proyek Pembangunan Dermaga Lanal Biak,” Bangunan, vol. 30, no. 2, pp. 111–120, 2025, doi: 10.17977/um071v30i22025p111-120.
[17] Y. Liu, L. Huang, X. Liu, G. Ji, X. Cheng, and E. Onstein, “A late-mover genetic algorithm for resource-constrained project-scheduling problems,” Information Sciences, vol. 642, art. no. 119164, 2023, doi: 10.1016/j.ins.2023.119164.
[18] S. Ben Issa, R. A. Patterson, and Y. Tu, “Solving resource-constrained project scheduling problems under different activity assumptions,” Computers & Industrial Engineering, vol. 180, art. no. 109170, 2023, doi: 10.1016/j.cie.2023.109170.
[19] J. F. da S. Coelho and M. Vanhoucke, “New resource-constrained project scheduling instances for testing (meta-)heuristic scheduling algorithms,” Computers & Operations Research, vol. 153, art. no. 106165, 2023, doi: 10.1016/j.cor.2023.106165.
[20] B. Tian, J. Zhang, E. Demeulemeester, Z. Chen, and H. Ali, “Integrated resource-constrained project scheduling and material ordering problem considering storage space allocation,” Computers & Industrial Engineering, vol. 185, art. no. 109608, 2023, doi: 10.1016/j.cie.2023.109608.
[21] Kementerian Pekerjaan Umum dan Perumahan Rakyat, Peraturan Menteri PUPR Nomor 1 Tahun 2022 tentang Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat. Jakarta, Indonesia, 2022.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Muhammad Zidane Ramadhan, Agung Budiwirawan

This work is licensed under a Creative Commons Attribution 4.0 International License.