Strategi Digitalisasi dalam Perhitungan Volume Bekisting untuk Menunjang Manajemen Konstruksi (Studi Kasus Mall Semarang)
DOI:
https://doi.org/10.31004/riggs.v5i2.10307Keywords:
Bekisting, Balok, Plat, Dynamo Revit, Bim, Quantity Take-Off, Mall Semarang.Abstract
Pekerjaan bekisting merupakan komponen kritis dalam konstruksi beton bertulang yang memerlukan akurasi tinggi, mengingat biayanya dapat mencapai 40–60% dari total biaya struktur beton serta berkontribusi signifikan terhadap limbah konstruksi. Penelitian ini bertujuan menganalisis perhitungan volume komponen bekisting pada balok dan plat menggunakan Dynamo Revit dengan studi kasus Mall Semarang. Metode kuantitatif deskriptif diterapkan melalui pemodelan struktur 3D di Autodesk Revit 2025 dan penyusunan skrip visual programming menggunakan Dynamo Revit. Model mencakup elemen kolom, balok, plat lantai, serta 17 jenis komponen penyusun bekisting (main frame, ladder frame, cross brace, joint pin, U head, balok suri-suri, besi hollow, kayu kaso, plywood, head scaffolding, pipe shoring, baseplate shoring, dan lain-lain) yang dimodelkan secara terpisah dalam bentuk family. Hasil penelitian menunjukkan bahwa pemodelan bekisting berhasil dilakukan secara lengkap dan terintegrasi. Penggunaan Dynamo Revit terbukti sangat efektif dengan akurasi 100% (selisih 0% terhadap perhitungan manual), efisiensi waktu perhitungan seluruh komponen hanya 10–15 menit setelah model selesai, serta kemampuan reusability skrip untuk perhitungan pada zona pengecoran yang berbeda (Zona A dan Zona B) tanpa perlu menyusun ulang dari awal. Perhitungan rinci menghasilkan, misalnya, jumlah scaffolding bawah 5.321 unit, total panjang hollow 189,01 m, luas plywood samping 11.883,66 m², dan seterusnya untuk satu lantai dasar. Validasi dengan perhitungan manual menunjukkan tidak ada perbedaan (deviasi 0%). Penelitian ini memberikan kontribusi praktis bagi adopsi BIM dan visual programming dalam manajemen konstruksi, serta menjadi referensi bagi praktisi dan akademisi dalam meningkatkan efisiensi quantity take-off bekisting.
Downloads
References
[1] B. Cheng, J. Huang, K. Lu, J. Li, G. Gao, T. Wang, and H. Chen, “BIM-enabled life cycle assessment of concrete formwork waste reduction through prefabrication,” Sustainable Energy Technologies and Assessments, vol. 53, art. no. 102449, 2022, doi: 10.1016/j.seta.2022.102449.
[2] A. Monteiro and J. Poças Martins, “A survey on modeling guidelines for quantity takeoff-oriented BIM-based design,” Automation in Construction, vol. 35, pp. 238–253, 2013, doi: 10.1016/j.autcon.2013.05.005.
[3] F. Ergen and Ö. H. Bettemir, “Development of ontological algorithms for exact QTO of reinforced concrete construction items,” Structures, vol. 60, art. no. 105907, 2024, doi: 10.1016/j.istruc.2024.105907.
[4] C. Khosakitchalert, N. Yabuki, and T. Fukuda, “Improving the accuracy of BIM-based quantity takeoff for compound elements,” Automation in Construction, vol. 106, art. no. 102891, 2019, doi: 10.1016/j.autcon.2019.102891.
[5] C. Khosakitchalert, N. Yabuki, and T. Fukuda, “Automated modification of compound elements for accurate BIM-based quantity takeoff,” Automation in Construction, vol. 113, art. no. 103142, 2020, doi: 10.1016/j.autcon.2020.103142.
[6] V.-H. Pham, P.-H. Chen, Q. Nguyen, and D.-T. Duong, “BIM-Based Automatic Extraction of Daily Concrete and Formwork Requirements for Site Work Planning,” Buildings, vol. 14, no. 12, art. no. 4021, 2024, doi: 10.3390/buildings14124021.
[7] S. Alathamneh, W. Collins, and S. Azhar, “BIM-based quantity takeoff: Current state and future opportunities,” Automation in Construction, vol. 165, art. no. 105549, 2024, doi: 10.1016/j.autcon.2024.105549.
[8] H. Liu, J. C. P. Cheng, V. J. L. Gan, and S. Zhou, “A knowledge model-based BIM framework for automatic code-compliant quantity take-off,” Automation in Construction, vol. 133, art. no. 104024, 2022, doi: 10.1016/j.autcon.2021.104024.
[9] M. Valinejadshoubi, O. Moselhi, I. Iordanova, F. Valdivieso, and A. Bagchi, “Automated system for high-accuracy quantity takeoff using BIM,” Automation in Construction, vol. 157, art. no. 105155, 2024, doi: 10.1016/j.autcon.2023.105155.
[10] F. Ergen and Ö. H. Bettemir, “Development of BIM software with quantity take-off and visualization capabilities,” Journal of Construction Engineering, Management & Innovation, vol. 5, no. 1, pp. 1–14, 2022, doi: 10.31462/jcemi.2022.01001014.
[11] T. Akanbi, J. Zhang, and Y.-C. Lee, “Data-driven reverse engineering algorithm development method for developing interoperable quantity takeoff algorithms using IFC-based BIM,” Journal of Computing in Civil Engineering, vol. 34, no. 5, art. no. 04020036, 2020, doi: 10.1061/(ASCE)CP.1943-5487.0000909.
[12] S. Kim, S. Chin, and S. Kwon, “A discrepancy analysis of BIM-based quantity take-off for building interior components,” Journal of Management in Engineering, vol. 35, no. 3, art. no. 05019001, 2019, doi: 10.1061/(ASCE)ME.1943-5479.0000684.
[13] D. Olsen and J. M. Taylor, “Quantity take-off using Building Information Modeling (BIM), and its limiting factors,” Procedia Engineering, vol. 196, pp. 1098–1105, 2017, doi: 10.1016/j.proeng.2017.08.067.
[14] J. Lee, Y.-J. Park, C.-H. Choi, and C.-H. Han, “BIM-assisted labor productivity measurement method for structural formwork,” Automation in Construction, vol. 84, pp. 121–132, 2017, doi: 10.1016/j.autcon.2017.08.009.
[15] Z. Mei, M. Xu, P. Wu, S. Luo, J. Wang, and Y. Tan, “BIM-based framework for formwork planning considering potential reuse,” Journal of Management in Engineering, vol. 38, no. 2, art. no. 04021090, 2022, doi: 10.1061/(ASCE)ME.1943-5479.0001004.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Mohammad Riyan Suryo Buwono, Muhammad Faizal Ardhiansyah Arifin

This work is licensed under a Creative Commons Attribution 4.0 International License.